minor changes
authorcamjan <jcampos004@ikasle.ehu.es>
Wed, 20 May 2015 16:41:28 +0000 (18:41 +0200)
committercamjan <jcampos004@ikasle.ehu.es>
Wed, 20 May 2015 16:41:28 +0000 (18:41 +0200)
It2Artifacts/2ndSprintPlanning~ [deleted file]
It2Artifacts/2ndSprintRetrospectiveMeeting~ [deleted file]
It3Artifacs/3rdSprintPlanning [deleted file]
It3Artifacs/3rdSprintPlanning~ [deleted file]

diff --git a/It2Artifacts/2ndSprintPlanning~ b/It2Artifacts/2ndSprintPlanning~
deleted file mode 100644 (file)
index a8a1a4a..0000000
+++ /dev/null
@@ -1,4 +0,0 @@
-The main topics discussed in the second sprint meeting are the following ones:
-       -The scrum master for this first sprint will be Eneko Pinzolas.
-       -The backlog will be the one uploaded to xp-dev.
-       -The main aim for the team in this second iteration will be developing almost all the stated use cases in the project statement.
diff --git a/It2Artifacts/2ndSprintRetrospectiveMeeting~ b/It2Artifacts/2ndSprintRetrospectiveMeeting~
deleted file mode 100644 (file)
index 77b919c..0000000
+++ /dev/null
@@ -1,13 +0,0 @@
-These are the main topics exposed in the 2nd sprint retroespective meeting and our conclusion:
-
-What have we done?
-
-        The client side was completely renovated with a new user friendly and fresh view, which has incorporated different filters when finding rural houses and offers. Apart from that we have added a new actor into the system called administrator who confirms the withdrawal and adittion of a house into the system. The owner actor now also has new features like modifying and deleting existing offers and houses.
-
-What haven't we done?
-
-       We have almost finished the use cases stated in the project statement, but we did not realize that our project was missing one of these use cases, the one of accepting booking from the owner side, so we have not developed the required code and artifacs for it.
-       
-What will we do?
-
-       First of all we will develop the new use case stated before, the one that was defined at the start of the project. Apart from that, we should include a client server feature to the current version and to deal with that we will have to modify our current business logic layer. If we fullfil all the things we have mentioned we should start including extra features into our application.
diff --git a/It3Artifacs/3rdSprintPlanning b/It3Artifacs/3rdSprintPlanning
deleted file mode 100644 (file)
index f229523..0000000
+++ /dev/null
@@ -1,5 +0,0 @@
-The main topics discussed in the third sprint meeting are the following ones:
-       -The scrum master for this third sprint will be Eneko Pinzolas.
-       -The backlog will be the one uploaded to xp-dev.
-       -The main aim for the team in this third iteration will be to develop the lacking use case and the client server application, apart from that
-       if we find extra time we will try to include extra features(to be discussed).
diff --git a/It3Artifacs/3rdSprintPlanning~ b/It3Artifacs/3rdSprintPlanning~
deleted file mode 100644 (file)
index da2a33d..0000000
+++ /dev/null
@@ -1,5 +0,0 @@
-The main topics discussed in the third sprint meeting are the following ones:
-       -The scrum master for this third sprint will be Eneko Pinzolas.
-       -The backlog will be the one uploaded to xp-dev.
-       -The main aim for the team in this third iteration will be to develop the lacking use case and the client server application, apart from that
-       if we find extra time we will try to include extra features.