All Iterations

Iteration Hours Dates Completed
Total Added Remaining
analysis of requirements for project 3 0 0 Tue 17 Dec, 2013Tue 31 Dec, 2013
14 days

100 %
design and specification 2 2 0 Tue 17 Dec, 2013Tue 31 Dec, 2013
14 days

100 %
implement software 3 0 3 Tue 17 Dec, 2013Tue 31 Dec, 2013
14 days

0 %
integration and system testing 2 0 2 Tue 17 Dec, 2013Tue 31 Dec, 2013
14 days

0 %
unallocated bugs and stories 0 0 0 Tue 17 Dec, 2013Tue 31 Dec, 2013
14 days

0 %
impliement euclidian algorith for two numbers 1 0 0 Tue 14 Jan, 2014Tue 28 Jan, 2014
14 days

100 %
Unallocated Bugs and Stories 0 0 0